325 Main Updates

325 MAIN CONSTRUCTION UPDATE—JULY- SEPTEMBER 2021

Please note as of January 18, 2021 the primary entrance to 355 Main Street is temporarily closed due to construction impacts through July 2021. To access the 355 Main Street lobby, please use the Pioneer Way entrance. Click here for a map showing the alternate path of entry.

  • Curtain Wall installation is substantially complete.
  • Tower Cranes #1 and #2 have been dismantled.
  • Mechanical/Electrical/Plumbing (MEP)/ and Fire Protection work continues to move up the building nearing completion.
  • Interior fit-outs progressing and nearing completion.
  • Loading Dock restoration progressing and nearing completion.
  • Medical Penthouse substantially complete and on schedule to commence in August.
  • Doors and Hardware being installed.
  • Main Lobby finishes continue to progress.
  • Stair F structure is substantially complete as finishes are ongoing.
  • MBTA submittals and coordination ongoing.
  • Green Garage work continues with sitework, landscaping, and facade work.

325 MAIN STREET PROJECT SUMMARY

Located in the heart of Kendall Square, 325 Main Street is the future home of a mixed-use building consisting of office space and three levels of retail/public spaces. While being fully-occupied by Google, this 16-story building will also feature a new public indoor connector at the street level and two new access points to the redesigned and reimagined rooftop garden. The project features an enhanced visual connection to the rooftop garden, as well as mezzanine spaces for additional outdoor seating and activation to complement the existing programming occurring on Kendall Plaza. Approximately 420,000 SF, this building will be complete in 4Q 2022.

GENERAL CONTRACTOR

Turner Construction

PHONE NUMBER TO CALL IN CASE OF UNSAFE CONDITIONS

(617) 247-5409

325 Main Street