What’s going on

150 150 Kendall Center

Utility Work in Ames Street:
Water and sewer line extensions into site. A slight lane shift may be required on Ames Street.

Sitework:
Connections from buildings utilities to the utilities in Ames Street. Majority of the work will be within the site’s fenced area.

Cast in Place Concrete:
South Side of Site: Install 4th floor Peri Skydeck. Install 4th floor beam and slab rebar. Pour concrete slab.

North Side of Site:
Rebar and formwork for level 4 columns. Pour concrete columns. Begin 5th floor Peri Skydeck install. Rebar and formwork deliveries for the duration of the week.

Miscellaneous;
The jobsite will be open this Saturday for all concrete related activities.

What’s coming up;
Continuing with concrete core walls, columns, and slab placements for the month of June. Exterior construction hoist install in July.